When Volvo set out to build a 1.5 million-square-foot manufacturing facility in the southeastern U.S., South Carolina and several surrounding states competed for the massive $5 billion investment. The project promised significant economic benefits, including thousands of jobs and long-term business growth.
South Carolina first proposed a site that had already made substantial progress in permitting, making it an early contender. However, when Volvo overlaid its design and future buildout plans onto the site, it became clear that the site was too small to accommodate the entire vision.
Around the same time, a competing site in Georgia happened to match Volvo’s needs perfectly. Although Volvo was considering the Georgia site, South Carolina still had a chance to win the investment – if it could propose an alternative site that was large enough and wouldn’t delay the project timeline.
Enter the Camp Hall site in Berkeley County, SC. Strategically located and adequately sized, it was ideal for Volvo’s long-term vision. Time was running out. Volvo needed to complete permitting quickly to meet its internal deadlines and proceed with the project.
Recognizing the urgency and importance, the State of South Carolina and the Department of Commerce turned to RES for a fast, scalable solution. RES is committed to delivering a full permittee-responsible mitigation (PRM) strategy to meet Volvo's environmental requirements within the tight timeframe. Not only did RES deliver—they did it faster than expected. Without a clear compensatory mitigation plan, the project would likely have faced permitting delays and increased costs, potentially disqualifying it from selection.
RES leveraged its permittee-responsible mitigation (PRM) expertise and robust internal resources to develop a best-in-class solution in an incredibly time-efficient manner. This ensured Volvo met its environmental compliance requirements without delaying the project timeline. Instead of relying on a single mitigation site, RES implemented a landscape-scale conservation strategy, focusing on restoring and preserving critical environmental resources across multiple properties.
This approach provided a watershed-scale solution that offset the Volvo facility's environmental impacts and strengthened South Carolina’s conservation network.
Key elements of the plan included:
By implementing these measures, RES eliminated the uncertainty that had initially led Volvo to consider Georgia, ensuring that South Carolina remained an attractive and environmentally responsible choice for the automaker.
With a clear and executable mitigation plan in place, the State of South Carolina and the Department of Commerce successfully secured Volvo’s investment. The project moved forward without permitting delays, and today, the Volvo manufacturing plant operates outside Charleston, SC, along Interstate 26.
This project demonstrates how environmental mitigation can be a strategic advantage. By partnering with RES, South Carolina transformed a regulatory challenge into a successful outcome, proving that the right mitigation strategy, backed by long-term stewardship and local partnerships, can help any large-scale project stay on track.